[BlockC]Progress in February 2018

By Monday March 12th, 2018 Construction Progress

PDF: Bodaiju-Site-Progress-Report_Vol.15-BlockC

MEP WORK (BUILDING C)
This is our site activities of MEP Work in this February 2018. These are our site progressing activities photos.
Picture1 Picture2
Picture3 Picture4

BRICK WALL WORK (BUILDING C)
This is our site activities of Brick Wall Work in this February 2018 of Building C of our project. This work start after finish structure work.
Picture5 Picture6
Picture7 Picture8

WALL PLASTERING WORK (BUILDING C)
This is our site activities of Wall Plastering Work in this February 2018. This plastering work is one of the important work to make nice wall finishing work.
Picture9 Picture10
Picture11 Picture12

WALL FINISHING WORK (BUILDING C)
This is our site activities of Wall Finishing Work in this February 2018. There are the combination of Brick Work, Plastering Work, Painting and Tiling Work as our wall finishing.
Picture13 Picture14
Picture15 Picture16

CEILING WORK (BUILDING C)
This is our site activities of Ceiling Work of Building C in this February 2018. We start from Framing, Paneling, Joining and Painting as the finishing.
Picture17 Picture18
Picture19 Picture20

FLOOR FINISHING WORK (BUILDING C)
This is our site activities of Floor Finishing Work with tiling of building C in this February 2018.
Picture21 Picture22
Picture23 Picture24

FITTING OUT WORK (BUILDING C)
This is our site activities of Fitting Out Work of building C in this February 2018. Door and Windows Installation progress activities photos.
Picture25 Picture26
Picture27 Picture28