Progress in September 2016

By Thursday October 6th, 2016 Construction Progress

Download PDF :Bodaiju Site Progress Report_Vol.11_Sep2016

7FL. SUPER-STRUCTURE COMPLETION-Sep. 2016
Picture1Picture2

SEPTEMBER 2016 SITE VIEW (BUILDING A & B)
In September 2016 we completed the 7th Floor Structure Work for Building A & B.
Picture24

7FL-BEAM & SLAB FORM WORK (BUILDING A & B)
Slab and Beam Form Work installation activities in our construction site in September 2016.
Picture25 Picture26

7FL-BEAM & SLAB REINFORCEMENT (BUILDING A & B)
Reinforcement Work site activities of Building A & B on 7th Floor which was completed in September 2016.
Picture27 Picture28

7FL-RE-BAR CHECK & CLEANING (BUILDING A & B)
Re-Bar Checking activates of Building A & B at the construction site by our engineers.
Picture29 Picture30

7FL-CONCRETE TEST AT SITE
Mixed-Concrete was tested at the site before casting building A & B Structure, Slab and Beam.
Picture31 Picture32

7FL-MEP WORK (BUILDING A & B)
Pipe for electricity on 7th Floor Slab was laid for concreting.
Picture33 Picture34

7FL-CONCRETE WORK (BUILDING A & B)
This is Concrete Work of Building A & B that was completed in September 2016.
Picture35 Picture36

WATER PIPE WORK (BUILDING A & B)
This is Water Piping Work of Building A & B that was completed in September 2016.
Picture37 Picture38

MASONRY WORK (BUILDING A & B)
MASONRY WORK is the brick work after finishing structure work on each floor. We have started this brick work for building A & B since September 2016.
Picture39 Picture40

WATERPOOF TEST & CEILING WORK (MOCK UP UNIT)
Waterproofing test and ceiling work in our site for mock up unit in building A.
Picture41 Picture42

DOOR FRAME & WAREDROPE WORK (MOCK UP UNIT)
Door Frame Installation for our mock up unit in building A.
Picture43 Picture44