Progress in October 2016

By Saturday November 5th, 2016 Construction Progress

Download PDF: Bodaiju-Site-Progress-Report_Vol.12_Oct2016

October 2016 Site View (Building A&B)
In October 2016 we completed the Structure Work on 8th Floor and reinforcement work on 9th Floor for Building A & B.

Picture18

9FL-BEAM & SLAB FORM WORK (BUILDING A & B)
Slab and Beam Form Work installation activities in our construction site in October 2016.
Picture2 Picture3

9FL-BEAM & SLAB REINFORCEMENT (BUILDING A & B)
Reinforcement Work site activities in Building A & B on 9th Floor have been completed in October 2016.
Picture4 Picture5

8FL-RE-BAR CHECK & CLEANING (BUILDING A & B)
Re-Bar Checking activates in Building A & B at construction site by our engineers.
Picture6 Picture7

8FL-CONCRETE TEST AT SITE
Mixed-Concrete was tested at the site before casting building A & B Structure, 8FL Slab and Beam.
Picture9 Picture8

8FL-MEP WORK (BUILDING A & B)
Pipe for electricity in 7th Floor Slab was laid to be ready for concreting.
Picture10 Picture11

8FL-CONCRETE WORK (BUILDING A & B)
Water Piping Work of Building A & B had been completed in September 2016.
Picture12 Picture13

MASONRY WORK (BUILDING A & B)
MASONRY WORK is the brick work after finish structure work in each floor. This is our site activities in October 2016.
Picture15 Picture14

BUILT-IN FURNITURE SETUP (MOCK UP UNIT)
Built-in Wardrobe and Hanging Kitchen’s cabinet installation activities for Mock Up units in Building A.
Picture17 Picture16