November 2016 Site View (Building A & B)
In November 2016 we completed the 10th Floor Structure Work and reinforcement work of 11th Floor for Building A & B.
11FL-BEAM & SLAB FORM WORK (BUILDING A & B)
Slab and Beam Form Work installation activities in our construction site in November 2016.
11FL-BEAM & SLAB REINFORCEMENT (BUILDING A & B)
Reinforcement Work site activities of Building A & B on 11th Floor which completed in this November.
10FL-RE-BAR CHECK & CLEANING (BUILDING A & B)
Re-Bar Checking activates of Building A & B at construction site by our engineer.
10FL-CONCRETE TEST AT SITE
Mixed-Concrete was tested at site before casting building A & B Structure, 10FL Slab and Beam.
MEP WORK (BUILDING A & B)
Pipe for electricity in 10th Floor Slab was laid to be ready for concreting and laid water piping system under the stab.
10FL-CONCRETE WORK (BUILDING A & B)
This is Water Piping Work of Building A & B was completed in November 2016.
MASONRY WORK (BUILDING A & B)
MASONRY WORK is the brick work after finish structure work in each floor. This is our site activities in November 2016.
PLASTERING WORK (BUILDING A & B)
PLASTERING WORK is the a layer of wall after brick work. Now we are processing Plastering Work from this November 2016.