Progress in November 2015

By Tuesday December 8th, 2015 Construction Progress

Download: Bodaiju Site Progress Report Vol.1 December-2015

UXO CLEARANCE WORK

In order to provide the utmost safety to all our future residents, we had conducted a bomb detection exercise in October 2015 and Bodaiju site is certified to be clear of bombs.  This exercise is essential as it is part of our construction safety guidelines.

UXO-Clearance-Work-01-300x225 UXO-Clearance-Work-02-300x225

UXO CLEARANCE SAFETY CERTIFICATE
Certificate No. : NPMEC, OPS/036/15

UXO-Clearance-Certificatte-212x300

PILING WORK

Piling works are being carried out by our dedicated and well trained construction team. The quality of piling is constantly being monitored in order to deliver the highest quality as it is a very important aspect for the foundation of a building.
Piling-Work-01 Piling-Work-02-300x224

TEST PILE WORK

Prior to the piling work, test piling works were completed on 16th November 2015. The purposes of test piling is to verify the capacity load of the piles and to ensure that piling work is aligned with our intended designs.

PDA-Test-Work-01-300x169 PDA-Test-Work-02-300x169