Progress in June 2016

By Monday July 18th, 2016 Construction Progress

Download PDF :  Bodaiju-Site-Progress-Report_Vol.8_July2016

PHOTOS OF PROGRESS COMPLETION
ConstructionProgress1 ConstructionProgress2

ConstructionProgress3 ConstructionProgress4

ConstructionProgress5 ConstructionProgress6

RE-BAR FABRICATION (BUILDING A & B)
Re-Bar fabrication activities at our workshop in construction site which completed the 1FL Super-Structure and we keep continue for upper floor.
ConstructionProgress7 ConstructionProgress8

FORM-WORK FABRICATION (BUILDING A & B)
Form-Work fabrication was completed for 1FL Super-Structure Work and we keep continue to fabricate for upper floor.
ConstructionProgress9 ConstructionProgress10

1FL-BEAM & SLAB FORM WORK (BUILDING A & B)
1FL Beam and Slab Form Work installation activities in our construction site. Currently we are preparing the Form Work for the upper floor.
ConstructionProgress11 ConstructionProgress12

1FL-BEAM & SLAB REINFORCEMENT (BUILDING A & B)
Reinforcement Work site activities of Building A & B on 1FL Level of the buildings which completed.
ConstructionProgress13 ConstructionProgress14

1FL-RE-BAR CHECK & CLEANING (BUILDING A & B)
Our engineers are doing the proper check and cleaning before casting concrete. We keep checking to bring quality for our valued clients.
ConstructionProgress15 ConstructionProgress16

1FL-CONCRETE TEST AT SITE
Mixed Concrete was tested at site before concreting of 1FL Level. We are following the quality standard to verify the quality from steps to steps in our construction site.
ConstructionProgress17 ConstructionProgress18

1FL-MEP WORK (BUILDING A & B)
Our engineer are laying the pipe for electricity in 1FL Slab before concreting. This is MEP Work activity after checking and waiting for concrete casting.
ConstructionProgress19 ConstructionProgress20

1F-CONCRETE WORK AT SITE
Concrete Work for 1st Floor Level of Building A & B was completed in June 2016. This is our concrete casting activities at our construction site during night time.
ConstructionProgress21 ConstructionProgress22

SITE VIEWS (BUILDING A & B)
In conclusion we already complete the 1st Floor Concreting Work (1FL Super-Structure Work) for Building A & B by 30th June 2016 as we plan in our schedule. We keep working hard with the standard quality and on our schedule for our valued clients.
ConstructionProgress23 ConstructionProgress24
ConstructionProgress25 ConstructionProgress26