Progress in January 2016

By Friday February 5th, 2016 Construction Progress

Download: Bodaiju Site Progress Report_Vol.3_February 2016

PILING WORK OF BUILDING B & PARKING
Piling work of Building A & B was completed and piling work of Parking  are progressing.
1-1   1-2

PILE CAP EXCAVATION WORK
Most Piles of Building A and Building B are excavated and some remaining in progress.
2-1   2-2

PILE CAP SOIL COMPACTION (BUILDING A & B)
After excavation, proper compaction is carried out to the soil and survey work is started before Lean Concrete Work.
3-1   3-2

LEAN CONCRETE WORK (BUILDING A & B)
After excavation and soil compaction, the foundation is prepared with Lean Concrete for Pile Cab Reinforcement.
4-1   4-2

PILE CAP REINFORCEMENT WORK (BUILDING A & B)
Installation of Pile Cab Reinforcement at Building A and Building B in progress before and after lean concretes.
5-1   5-2

FORM WORK (BUILDING A & B)
Erection and production of Pile Cab’s Form Work are processing everyday at site.
6-1   6-2

CONCRETE TESTING (BUILDING A & B)
We do the proper test at site to verified the quality of the concrete before casting to ensure the quality before casting.
7-1   7-2

PILE CAB CONCRETE CASTING (BUILDING A & B)
Our pile cab of Building A & B are progressing at site and casting with the proper concrete specification and vibration. Now we already completed 40%.
8-1   8-2