Progress in February 2016

By Friday March 4th, 2016 Construction Progress

Download PDF :Bodaiju Site Progress Report_Vol.4_March 2016

PILING WORK OF PHASE 1
Piling work of Building A & B and Car Parking was completed with the proper load test. Now we are continuing to do the Sub-Structure Work as a step to RC-Superstructure.
Feb2016_1-1 Feb2016_1-2

SUB-STRUCTURE WORK
Sub-Structure Work is progressing at site parallel along with Ground Beam Work for completing Foundation Work at the end of this March.
Feb2016_2-1 Feb2016_2-2

PILE CAP’s RE-BAR WORK (BUILDING A & B)
After Re-Bar and Formwork we do the proper concrete test and then we casted the concrete for pile caps.
Feb2016_3-1 Feb2016_3-2

PILE CAP’s FORM WORK (BUILDING A & B)
This is our site activity which do the Formwork for Pile Cab.
Feb2016_4-1 Feb2016_4-2

PILE CAP’s CONCRETE CASTING (BUILDING A & B)
After Re-Bar and Formwork, we do the proper concrete test at site and casted the pile cap.
Feb2016_5-1 Feb2016_5-2

PILE CAP WORK (BUILDING A & B)
Currently Pile Cap Work of Building A & B are completed in February. Pile Cap of Car Parking plan to finish by end of this March also.
Feb2016_6-1 Feb2016_6-2

GROUND BEAM’s RE-BAR WORK (BUILDING A & B)
We are doing and checking this Re-Bar by following drawing and specification before and after formwork for casting concrete.
Feb2016_7-1 Feb2016_7-2

GROUND BEAM’s FORM WORK (BUILDING A & B)
Form Work activates at site for Ground Beam Work, we had completed some Ground Beam concrete casting and some are in progress currently.
Feb2016_8-1 Feb2016_8-2

CONCRETE TEST AT SITE
We are performing the accurate concrete testing at site every time before casing concrete for Ground Beam.
Feb2016_9-1 Feb2016_9-2

GROUND BEAM’s CONCRETE CASTING
Ground Beam Concrete Casting Activities at site and we plan to complete this Foundation of Building A & B at the end of this March 2016.
Feb2016_10-1 Feb2016_10-2