[BlockA&B]Progress in December 2016

By Monday January 9th, 2017 Construction Progress

Download PDF: Bodaiju-Site-Progress-Report_Vol.14_Dec2016

Bodaiju-Site-Progress-Report_Vol.14_Dec2016
In this December 2016 we completed the 12th Floor Structure Work and the 13th Floor Reinforcement Work for Building A & B.
Picture1

13FL-BEAM & SLAB FORM WORK (BUILDING A & B)
Slab and Beam Form Work installation activities in our construction site for 13FL structure in December 2016.
Picture2 Picture3

13FL-BEAM & SLAB REINFORCEMENT (BUILDING A & B)
Reinforcement Work site activities of Building A & B on 13th Floor which completed in this December.
Picture4 Picture5

12FL-RE-BAR CHECK & CLEANING (BUILDING A & B)
12th Floor’s Re-Bar Checking and cleaning activates of Building A & B at construction site by our engineer before casting concrete.
Picture7 Picture6

12FL-CONCRETE TEST AT SITE
Mixed-Concrete was tested at the site before casting building A & B Structure, 12FL Slab and Beam.
Picture8 Picture9

MEP WORK (BUILDING A & B)
Pipes for electricity in 12FL Slab was laid to be ready for concreting and laid water piping system under the stab.
Picture10 Picture11

12FL-CONCRETE WORK (BUILDING A & B)
This is Concrete Casting Work for 12FL Slab and Beam of Building A & B was completed in December 2016.
Picture12 Picture13

MASONRY WORK (BUILDING A & B)
Masonry Work is the brick work after finish structure work of each floor. This is our site activities in this December 2016.
Picture14 Picture15

PLASTERING WORK (BUILDING A & B)
Plastering Work is a layer of the wall after brick work. Currently we are processing Plastering Work in Building A & B.
Picture16 Picture17

CEILING WORK (BUILDING A & B)
In this December 2016, we started the Ceiling Work for our interior work in Building A & B. These are our activity photos at the construction site inside Building A & B.