PILING WORK OF BUILDING B
Piling work of Building A was completed and piling work of Building B has commenced. Overall piling work of Building A and B is 73.5% complete.
PILE CAP EXCAVATION WORK
Since the completion of piling works for Building A, Pile Cap Excavation Work has commenced to provide a stable foundation. Pile Cap is the starting point of all footing (foundation) related works.
PILE CAP SOIL COMPACTION (BUILDING A)
After excavation, proper compaction is carried out to the soil and survey work is started before Lean Concrete Work.
LEAN CONCRETE WORK (BUILDING A)
After excavation and soil compaction, the foundation is prepared with Lean Concrete for Pile Cab Reinforcement.
PILE CAP REINFORCEMENT WORK (BUILDING A)
While piling at Building B is smoothly underway, installation of Pile Cap Reinforcement at Building A is also in good progress.
FORM WORK (BUILDING A)
Erection of Pile Cap Form Work has started.
SAFETY PRACTICE ACTIVITIE
Regular safety briefings are held on site, where safety shoes, uniforms and helmets are distributed to workers.
CUSTOMERS SITE VISIT EVENT
On 19th December 2015, valued customers were invited to our sales gallery, where they were offered refreshments and briefed on current construction progress and activities.
Our customers were also invited to visit our construction site by our engineers, in order to gain a better understanding of construction progress.