Progress in December 2015

By Wednesday January 6th, 2016 Construction Progress

Download: Bodaiju Site Progress Report Vol.2 January-2016

PILING WORK OF BUILDING B
Piling work of Building A was completed and piling work of Building B has commenced. Overall piling work of Building A and B is 73.5% complete.

1-1-300x171 1-2-300x172

PILE CAP EXCAVATION WORK
Since the completion of piling works for Building A, Pile Cap Excavation Work has commenced to provide a stable foundation. Pile Cap is the starting point of all footing (foundation) related works.

2-1-300x172 2-2-300x171

PILE CAP SOIL COMPACTION (BUILDING A)
After excavation, proper compaction is carried out to the soil and survey work is started before Lean Concrete Work.

3-1-300x171 3-2-300x171

LEAN CONCRETE WORK (BUILDING A)
After excavation and soil compaction, the foundation is prepared with Lean Concrete for Pile Cab Reinforcement.

4-1-300x171 4-2-300x171

PILE CAP REINFORCEMENT WORK (BUILDING A)
While piling at Building B is smoothly underway, installation of Pile Cap Reinforcement at Building A is also in good progress.

5-1-300x172 5-2-300x171

FORM WORK (BUILDING A)
Erection of Pile Cap Form Work has started.

6-1-300x172 6-2-300x171

SAFETY PRACTICE ACTIVITIE
Regular safety briefings are held on site, where safety shoes, uniforms and helmets are distributed to workers.

7-1-300x172 7-2-300x172

CUSTOMERS SITE VISIT EVENT
On 19th December 2015, valued customers were invited to our sales gallery, where they were offered refreshments and briefed on current construction progress and activities.

 

8-3-300x170 8-4-300x171

Our customers were also invited to visit our construction site by our engineers, in order to gain a better understanding of construction progress.

8-1-300x171 8-2-300x171