Progress in August 2016

By Friday September 9th, 2016 Construction Progress

Download PDF :Bodaiju-Site-Progress-Report_Vol.10_Sep2016

JULY 2016 SITE VIEW (BUILDING A & B)
In August 2016 we already complete the 5th Floor Structure Work for Building A & B as we planned to compete 7th Floor Concreting Work by end of October 2016
Picture1Picture2
Picture3Picture4

5FL-BEAM & SLAB FORM WORK (BUILDING A & B)
Slab and Beam Form Work installation activities in our construction site in August 2016.
Picture5 Picture6

5FL-BEAM & SLAB REINFORCEMENT (BUILDING A & B)
Reinforcement Work site activities of Building A & B on 5th Floor which completed.
Picture7 Picture8

5FL-RE-BAR CHECK & CLEANING (BUILDING A & B)
Re-Bar Checking activates of Building A & B at construction site by our engineer.
Picture9 Picture10

5FL-CONCRETE TEST AT SITE
Mixed-Concrete was tested at site before casting building A & B Structure, Slab and Beam.
Picture11 Picture12

5FL-MEP WORK (BUILDING A & B)
Pipe for electricity in 5th Floor Slab was laid and our engineer checking strictly on MEP works to be ready for concreting.
Picture13 Picture14

5F-CONCRETE WORK AT SITE
Concrete Work for 5th Floor Level of Building A & B was completed in August 2016. This is level checking after casting concrete.
Picture15 Picture16

PLASTERING WORK (MOCK UP UNIT)
Plastering work in our site for our mock up unit in building A already start in this August.
Picture17 Picture18

MEP WORK (MOCK UP UNIT)
MEP work in our site for our mock up unit in building A also started in this August.
Picture19 Picture20