Progress in May 2016

By Friday June 3rd, 2016 Construction Progress

Download PDF :Bodaiju Site Progress Report_Vol.7_Jun 2016

TOWER CRANE INSTALLATION (BUILDING A & B)
We was done basement for installing our Tower Crane in Block A &  B.
7-2-1 7-2-2

7-2-3 7-2-4

NHK TELEVISON INTERVIEW & SITE VISIT (BUILDING A & B)
In May 2016, there was an interview from NHK Television of Japan while our management visited Bodaiju Construction Site.
7-3-1 7-3-2

7-3-3 7-3-4

RE-BAR FABRICATION (BUILDING A & B)
We are fabricating the Re-Bar for Superstructure Work of Building A & B at our workshop in construction site.
7-4-1 7-4-2

FORM-WORK FABRICATION (BUILDING A & B)
We are fabricating the Form-Work for Superstructure Work of Building A & B at our workshop in construction site.
7-5-1 7-5-2

P2-BEAM & SLAB FORM WORK (BUILDING A & B)
We are doing the Form Work of Building A & B on P2 Level of the buildings.
7-6-1 7-6-2

P2-BEAM & SLAB REINFORCEMENT (BUILDING A & B)
We are doing the Reinforcement Work of Building A & B on P2 Level of the buildings.
7-7-1 7-7-2

P2-RE-BAR CHECK & CLEANING (BUILDING A & B)
After we finished Form-Work and Reinforcement Work, our engineers are doing the proper check and cleaning before casting concrete.
7-8-1 7-8-2

P2-CONCRETE TEST AT SITE
Before casting concrete for our Beam and Slab of P2 Level,  we are following the quality standard to verify the mixed concrete which delivery to our site.
7-9-1 7-9-2

P2-CONCRETE WORK (BUILDING A & B)
Concrete casting P2 Level of Building A & B was completed in May 2016. Now we are preparing the 1F Level Superstructure Work which plan to complete by end of this June 2016.
7-10-1 7-10-2

7-10-3 7-10-4

SITE VIEWS (BUILDING A & B)
In conclusion we already complete the P2 concreting work for Building A & B. We plan to finish the concrete work for 1F by the end of this June 2016. Currently we are under progress of Column Work and 1F Bean and 1F Slab Work.
7-11-1 7-11-2

7-11-3 7-11-4