MARCH 2017 SITE VIEW (BUILDING A & B)
Now April 2017 we are focusing on our Architectural Work and Interior Work for Building A & B.
Picture1

WATERPROOFING WORK (BUILDING A & B)
Waterproofing Work activities progress photos of this May 2017 in Building A & B.
Picture2 Picture3

MEP WORK (BUILDING A & B)
Mechanical, Electrical and Plumbing Work in Building A & B of our project.
Picture4 Picture5

MASONRY WORK (BUILDING A & B)
Masonry Work of Building A & B was completed by this May 2017.
Picture6 Picture7

PLASTERING WORK (BUILDING A & B)
This is March Plastering Work activities in our construction site after Masonry Work.
Picture8 Picture9

CEILING WORK (BUILDING A & B)
Ceiling Work is progressing in our construction site in Building A & B.
Picture10 Picture11

WALL FINISHING WORK (BUILDING A & B)
Wall skim coat activities after plastering work for Building A & B in this May 2017.
Picture12 Picture13

FLOOR FINISHING WORK (BUILDING A & B)
These are our activity’s of Floor Finishing (Tiling) photos inside of Building A & B.
Picture14 Picture15

FITTING WORK (BUILDING A & B)
Door and Window fitting Work activities at Building A & B in our construction site.
Picture16 Picture17

BUILD-IN CABINET WORK (BUILDING A & B)
These are our activity’s of Build-In Cabinet at construction site inside Building A & B such as Kitchen Counter, Hanging Cabinet and other Build-in Cabinet.
Picture18 Picture19Picture20 Picture21