[BlockC]Progress in September 2017

By Monday October 16th, 2017 Construction Progress

PDF: Bodaiju-Site-Progress-Report_Vol.6-BlockC

RE-BAR FABRICATION WORKSHOP (BUILDING C)
We have a workshop inside our site to fabricate Re-Bar for our Building C Structure.
Picture1 Picture2

FORM-WORK FABRICATION WORKSHOP (BUILDING C)
We have a workshop inside our site to fabricate Form-Work for our Building C Structure.
Picture3 Picture4

9F_COLUMN FORM AND RE-BAR WORK (BUILDING C)
This is our site activities for Form Work and Re-bar Work in this September. 2017
Picture5 Picture6

9F_REINFORCEMENT CHECK WORK (BUILDING C)
This is our inspection work for Reinforcement Work of Column in Building C, activities in this September 2017.
Picture7 Picture8

9F_SLAB FORM WORK (BUILDING C)
This is our site activities for Form Work of 9FL floor slab before we install the reinforcement bars.
Picture10 Picture9

9F_SLAB REINFORCEMENT WORK (BUILDING C)
Installation of Reinforcement for 9FL Floor Slab at Building C, activities in this September 2017.
Picture11 Picture12

9FL_CONCRETE TESTING WORK (BUILDING C)
In this September 2017, We casted concrete for 9FL Floor. This is our activities of concrete testing at site before casting our stair/slab.
Picture13 Picture14

9F_SLAB CONCRETE WORK WORK (BUILDING C)
This is 9FL floor Slab concrete work for our Building C which completed in this September 2017 as our schedule.
Picture15 Picture16