[BlockC]Progress in October 2017

By Friday November 10th, 2017 Construction Progress

PDF: Bodaiju-Site-Progress-Report_Vol.10-BlockC

RE-BAR FABRICATION WORKSHOP (BUILDING C)
We have a workshop inside our site to fabricate Re-Bar for our Building C Structure.
Picture1 Picture2

FORM-WORK FABRICATION WORKSHOP (BUILDING C)
We have a workshop inside our site to fabricate Form-Work for our Building C Structure.
Picture3 Picture4

10F_COLUMN FORM AND RE-BAR WORK (BUILDING C)
This is our site activities for Form Work and Re-bar Work in this October 2017.
Picture5 Picture6

10F_REINFORCEMENT CHECK WORK (BUILDING C)
This is our inspection work for Reinforcement Work of Column in Building C, activities in this October 2017.
Picture7 Picture8

11F_SLAB FORM WORK (BUILDING C)
This is our site activities for Form Work of 11FL floor slab before we install the reinforcement bars.
Picture9 Picture10

11F_SLAB REINFORCEMENT WORK (BUILDING C)
Installation of Reinforcement for 11FL Floor Slab at Building C, activities in this October 2017.
Picture11 Picture12

11FL_CONCRETE TESTING WORK (BUILDING C)
In this October 2017, We casted concrete for 11FL Floor. This is our activities of concrete testing at site before casting our slab.
Picture13 Picture14

11F_SLAB CONCRETE WORK WORK (BUILDING C)
This is 11FL floor Slab concrete work for our Building C which completed in this October 2017 as our schedule.
Picture15 Picture16