RE-BAR FABRICATION WORKSHOP (BUILDING C)
We have a workshop inside our site to fabricate Re-Bar for our Building C Structure.
FORM-WORK FABRICATION WORKSHOP (BUILDING C)
We have a workshop inside our site to fabricate Form-Work for our Building C Structure.
12F_COLUMN FORM AND RE-BAR WORK (BUILDING C)
This is our site activities for Form Work and Re-bar Work in this November 2017.
12F_REINFORCEMENT CHECK WORK (BUILDING C)
This is our inspection work for Reinforcement Work of Column in Building C, activities in this November 2017.
13F_SLAB FORM WORK (BUILDING C)
This is our site activities for Form Work of 13FL floor slab before we install the reinforcement bars.
13F_SLAB REINFORCEMENT WORK (BUILDING C)
Installation of Reinforcement for 13FL Floor Slab at Building C, activities in this October 2017.
13FL_CONCRETE TESTING WORK (BUILDING C)
In this November 2017, We casted concrete for 13FL Floor. This is our activities of concrete testing at site before casting our slab.
13F_SLAB CONCRETE WORK WORK (BUILDING C)
This is 13FL floor Slab concrete work for our Building C which completed in this November 2017.
WALL FINISHING WORK (BUILDING C)
In this November 2017, We already start Wall Finishing Work by Brick Work, Plastering Work and Skim Coating Work.
CEILING WORK (BUILDING C)
After we finish our plastering work and also started Celling Work of Building C. This is our site activities in this November.
FLOOR FINISHING WORK (BUILDING C)
This is our site activities of Floor Finishing Work with tiling of building C in this November 2017.
FITTING OUT WORK (BUILDING C)
This is our site activities of Fitting Out Work. Door Installation works of building C in this November 2017.