[BlockC]Progress in June 2017

By Friday July 7th, 2017 Construction Progress

PDF: Bodaiju-Site-Progress-Report_Vol.6-BlockC

RE-BAR FABRICATION WORKSHOP (BUILDING C)
We have a workshop inside our site to fabricate Re-Bar for our Building C Structure.
Picture1 Picture2

FORM-WORK FABRICATION WORKSHOP (BUILDING C)
We have a workshop inside our site to fabricate Form-Work for our Building C Structure.
Picture3 Picture4

3F_COLUMN REINFORCEMENT WORK (BUILDING C)
This is our site activities for 3FL floor Column Reinforcement Work in Building C.
Picture5 Picture6

3F_MEP WORK (BUILDING C)
Electricity piping system work for 3FL floor of Building C in June 2017.
Picture7 Picture8

3F_SLAB FORM WORK (BUILDING C)
This is our site activities for Form Work of 3FL floor slab before we install the reinforcement bars.
Picture9 Picture10

3F_SLAB REINFORCEMENT WORK (BUILDING C)
Installation of Reinforcement for 3FL Floor Slab at Building C, activities in this May 2017.
Picture11 Picture12

3F_SLAB CONCRETE TESTING WORK (BUILDING C)
This is our site activities of concrete testing at site before casting.
Picture13 Picture14

3FL_SLAB CONCRETE WORK WORK (BUILDING C)
This is 3FL floor Slab concrete work for our Building C which completed in this June 2017.
Picture15 Picture16

5F_SLAB & BEAM FORM WORK (BUILDING C)
These are our activities of Form Work in 5FL floor as a stage of structure work.
Picture17 Picture18

5F_BEAM & SLAB REINFORCEMENT WORK (BUILDING C)
Now we are working on 5FL floor Beam and Slab reinforcement work.
Picture19 Picture20