[BlockC]Progress in December 2016

By Tuesday January 10th, 2017 Construction Progress

Download PDF: Bodaiju-Site-Progress-Report_Vol.1_Dec2016-BlockC

UXO CLEARANCE WORK (BUILDING C)
Picture1 Picture2

UXO CLEARANCE SAFETY CERTIFICATE
In order to provide the utmost safety to all our future residents, we had conducted a bomb detection exercise in October 2015 and Bodaiju site is certified to be clear of bombs. This exercise is essential as it is part of our construction safety guidelines.
Picture3

PILING WORK (BUILDING C)
Building C, Piling works are being carried out and completed in November 2017.
Picture4 Picture5

TEST PILE WORK (BUILDING C)
Prior to the piling work, test piling works were completed in December 2017. This test pile is to verify the capacity load of that piles and it is aligned with our intended designs.
Picture6 Picture7

PILE CAP SOIL LEVELING WORK (BUILDING C)
After excavation, proper compaction is carried out to the soil and survey work is started before Lean Concrete Work.
Picture8 Picture9

LEAN CONCRETE WORK (BUILDING C)
After excavation and soil compaction, the foundation is prepared with Lean Concrete for Pile Cab Reinforcement.
Picture10 Picture11

PILE CAP REINFORCEMENT WORK (BUILDING C)
Installation of Pile Cab Reinforcement at Building C are commenced in this December 2016.
Picture12 Picture13

FORM WORK (BUILDING C)
Erection of Pile Cab Form Work and Installation are started at site since this December 2016.
Picture14 Picture15