[BlockA&B]Progress in June 2017

By Wednesday July 5th, 2017 Construction Progress

Download PDF: Bodaiju-Site-Progress-Report_Vol.20_June2017

PHOTOS OF PROGRESS COMPLETION – BUILDING A
Picture1

PHOTOS OF PROGRESS COMPLETION- BUILDING A
Picture2

MASONRY WORK (BUILDING A & B)
After Super Structure Work
Masonry Work of Building A & B was completed.
Picture3 Picture4

PLASTERING WORK (BUILDING A & B)
After Masonry Work
Plastering Work of Building A & B was completed.Picture5 Picture6

WALL SKIM COAT WORK (BUILDING A & B)
After Plastering Work
Skim Coat Work of Building A & B was completed.
Picture7 Picture8

LAYER PAINTING WORK (BUILDING A & B)
After Skim Coat Work, Brick Wall Work Completed by June 2017.
1st Layer Painting Work of Building A & B is progressing.
Picture9 Picture10

FLOOR FINISHING WORK (BUILDING A & B)
These are our activity’s of Floor Finishing (Tiling) photos inside of Building A & B.
Picture11 Picture12

FITTING WORK (BUILDING A & B)
Door and Window fitting Work activities at Building A & B in our construction site.
Picture13 Picture14

BUILD-IN CABINET WORK (BUILDING A & B)
Picture15 Picture16
Picture17 Picture18