[BlockA&B]Progress in January 2017

By Monday February 6th, 2017 Construction Progress

Download PDF: Bodaiju-Site-Progress-Report_Vol.15_Jan2017

DECEMBER 2016 SITE VIEW (BUILDING A & B)
In this December 2016 we already completed the 12th Floor Structure Work and reinforcement work of 13th Floor for Building A & B.

Picture1

14FL-BEAM & SLAB FORM WORK (BUILDING A & B)
Slab and Beam Form Work installation activities in our construction site for 14FL structure in December 2016.
Picture2 Picture3

14FL-BEAM & SLAB REINFORCEMENT (BUILDING A & B)
Reinforcement Work site activities of Building A on 14th Floor which completed in this January 2017.
Picture4 Picture5

13FL-RE-BAR CHECK & CLEANING (BUILDING A & B)
13th and 14th Floor’s Re-Bar Checking and cleaning activates of Building A & B at construction site by our engineer before casting concrete.
Picture6 Picture7

13FL-CONCRETE TEST AT SITE
Mixed-Concrete was tested at site before casting building A & B Structure, 12FL Slab and Beam.
Picture8 Picture9

MEP WORK (BUILDING A & B)
Pipes for electricity in 13FL Slab was laid to be ready for concreting and laid water piping system under the stab.
Picture10 Picture11

13FL-CONCRETE WORK (BUILDING A & B)
This is Concrete Casting Work for 13FL Slab and Beam of Building A & B was completed in January 2017.
Picture12 Picture13

MASONRY WORK (BUILDING A & B)
Masonry Work is the brick work after finish structure work of each floor. This is our site activities in this January 2017.
Picture14 Picture15

PLASTERING WORK (BUILDING A & B)
Plastering Work is a layer of the wall after brick work. Currently we are processing Plastering Work in Building A & B.
Picture16 Picture17

CEILING WORK (BUILDING A & B)
December 2016, we started the Ceiling Work in Building A & B. These are our activity’s photos at construction site inside Building A & B in this January 2017.
Picture18 Picture19

WALL FINISHING WORK (BUILDING A & B)
One of Interior Work, wall skim coat was commencing for Building A & B in this January 2017.
Picture20 Picture21

FLOOR FINISHING WORK (BUILDING A & B)
In this January 2017, We started the Floor Finishing Work as a scope of interior work in Building A & B. These are our activity’s photos at construction site inside Building A & B.
Picture22 Picture23
Picture24 Picture25